Wednesday, December 28, 2016

Our team met Tuesday evening to discuss further plans to accomplish our goals. A rough timeline of deadlines were mapped out to ensure success. One of things included on the timeline was to meet with Eric to discuss our final presentation. We plan to get have a rough draft of our presentation by next Monday to discuss. Further discussions were made regarding the design of the connection of the two piece frame. Mounting of the solar panel onto the frame solutions were discussed and listed. We will look further into these options and look for advice before finalizing.

Wednesday, November 9, 2016

Team Meeting to Review Outcomes

After a meeting with Eric and further discussion with the team, below outlines the expected goals for the rest of this semester.


  1. Abandon solar tracking portion of the project
  2. Further calculate and measure energy consumption of bogies
  3. Calculate and measure energy produced by solar panels
  4. Charging equipment: circuit diagram, calculations, organization of wiring schematic, quick disconnects, revise wire sizing according to NEMA standards for safety
  5. Redesign framework using ribs made from prebent aluminum bars produced by the manufacturing team and box frame made from aluminum stock similar to the track.
  6. Design detachable panel to mount charging equipment onto solar panel framework
  7. Test every piece of equipment to ensure compatibility and functionality.
Additional revisions to these outlines will include finer details and steps to complete task along with members responsible for each task.

Wednesday, October 26, 2016

Week 10/19 - 10/26

We spend all week preparing for Presentation 2

Sunday, October 16, 2016

WEEK 10/12 to 10/18

  • This week we measured both current and voltage of the bogie.
  • We are still working for a letter template for sponsorship.
  • We got familiarized with the specification of the charging controller SKYRC IMAX B6AC V2, and are attempting to start calculations.



Saturday, October 8, 2016

Minutes from Saturday Meeting

Monday Agenda:
Execute test on bogie for voltage and current draw.
Figure out how to continuously run bogie at max load.
Begin calculations with data obtained to expolate for 24 hours
Compile list of component that draw power on bogie

Sponsorship:
Compile list of solar companies
Find contacts
Refine letter

Solar Tracking:
Prototype idea
Pseudocode

Split weekly blog responsibilities

Wednesday, September 21, 2016

LINK TO GANTT CHART

https://docs.google.com/spreadsheets/d/1ohp6Y3q-qVPcegaHiYf-0ACPdmJpzVYYciGi4TYRckA/edit?usp=sharing

Week of 9/21/16

Figure out what to present
Solidworks
Inventory list update

Wednesday, September 14, 2016

Results of Wednesday Meet

To Do List

  • Get Solidworks working for all team members
  • Inventory of equipment
  • Finish reviewing prior year’s design, Solidworks design files
  • Determine equipment to carry over versus dispose of
  • Calculation of current solar panels
  • Update Gant chart per Eric's request

Week 9/7 - 9/14

This week our team consulted a previous student that has previously worked on the project last year. He advised us that is not efficient to use actuators to follow the sun, and this made us starting thinking about how to change the mounting for the solar panel. We concluded that the mounting will have a disk with multiple different perforations at different angles. We also decided to make make the mounting mechanism out of metal. We also decided to use different kind of batteries.

Thursday, September 8, 2016

  • Contact Information:

    Susana Guzman - susanaguzmanis@gmail.com

    Derick Wong - derick.wong@sjsu.edu

    Alan Yoc - alan.yoc@sjsu.edu

    Proposal Narrative
    • Setup and deconstruct prior year's prototype
    • Review prior year's documents and designs
    • Develop a solar tracking mechatronics system
    • Find a way to connect the new design with solar tracking to the existing Spartan Superway track.
    • Repair and improve battery charging to power 10  1/12 bogie.


    Scheduled Weekly Meeting: Fridays 5:00pm

    Availability:

    Susana - Mon 9:00am -11:30 am, 1:30 pm - 5:30pm, Tues/Thurs 12:00pm - 7:00pm, Wed 9:00am - 11:30 am, Friday any time before 5:45pm, Sat any time

    Derick: Tuesdays after 3 PM, Wednesdays 10 AM to 4:15 PM, Fridays after 4 PM, any time on Saturday or Sunday

    Alan: Monday 6pm - 9pm, Tuesday 9am - 12pm, Thursday 3pm - 9pm, Friday anytime before 6, Saturday anytime.

    Goals and Visions
    • Develop a solar power system to deliver power to the 1/12 scale bogie
    • Design a mounting and structural support for the solar panels to power the 1/12 panel
    • Explore opportunities to increase efficiency of solar panel via placement